Welcome to The Sheds, Invivolink. We are excited to have you all.
http://www.tennessean.com/story/money/real-estate/2014/04/28/invivolink-headed-sheds-charlotte/8409509/
Monday, April 28, 2014
Wednesday, April 23, 2014
Connector Bridge
The Sheds have a connector bridge that joins the 2nd floors of the two buildings. These photos show the steel being erected for this connector.
Thursday, April 10, 2014
Concrete permieter foundations
The weather is finally cooperating enough to pour concrete. Building C perimeter is poured in preparation to start wall framing.
Site Infrastructure
We are installing all of the storm water, sewer and water infrastructure now. These are deep connections!
Spring finally arrived
I have a back log of post to catch up on this project. Fortunately, the weather is much better and we can start making good progress on construction. The last post showed the steel that is being installed for the new second floor, here is a time lapse video capturing the process.