Wednesday, July 16, 2014
Monday, July 14, 2014
Translucent Panels
One of the unique design features of The Sheds is the translucent panel on the Charlotte facing facade of the buildings. This material allows a nice filtered light in during the day and will produce a lantern like glow on the outside at night. Installation of the panels has begun.
ForceX coming to The Sheds
We are thrilled to announce ForceX is leasing the balance of the space at the Sheds. We look forward to seeing you all occupy this very unique space in Nashville.
http://www.tennessean.com/story/money/2014/06/26/forcex-headquarters-nashville-expansion/11376391/
http://www.tennessean.com/story/money/2014/06/26/forcex-headquarters-nashville-expansion/11376391/
Friday, June 6, 2014
Site Work
Most of the underground work is complete (water, sewer, storm water) and we can start getting the parking lot in shape.
View from the Top
This is the view from the 2nd floor of the middle building. Somewhat obstructed as guys were welding near by and I could not get closer, but a general idea of what will be a good view of the Nashville skyline.
Connector Bridge
Here is a fast video showing the construction of the connector bridge between the Sheds and some other site work that has happened over the past few weeks.
Monday, April 28, 2014
Announcing First Tenant
Welcome to The Sheds, Invivolink. We are excited to have you all.
http://www.tennessean.com/story/money/real-estate/2014/04/28/invivolink-headed-sheds-charlotte/8409509/
http://www.tennessean.com/story/money/real-estate/2014/04/28/invivolink-headed-sheds-charlotte/8409509/
Wednesday, April 23, 2014
Connector Bridge
The Sheds have a connector bridge that joins the 2nd floors of the two buildings. These photos show the steel being erected for this connector.
Thursday, April 10, 2014
Concrete permieter foundations
The weather is finally cooperating enough to pour concrete. Building C perimeter is poured in preparation to start wall framing.
Site Infrastructure
We are installing all of the storm water, sewer and water infrastructure now. These are deep connections!
Spring finally arrived
I have a back log of post to catch up on this project. Fortunately, the weather is much better and we can start making good progress on construction. The last post showed the steel that is being installed for the new second floor, here is a time lapse video capturing the process.
Monday, January 20, 2014
Adding a 2nd Floor
The steel that is creating the new second floor in Shed, building A, began to be installed. The first new foundations are going in as well. Not the most immediately gratifying, but it is good progress and preparing the way for the new exterior skin.
A view from the courtyard:
A view from the courtyard: