Most of the underground work is complete (water, sewer, storm water) and we can start getting the parking lot in shape.
Friday, June 6, 2014
View from the Top
This is the view from the 2nd floor of the middle building. Somewhat obstructed as guys were welding near by and I could not get closer, but a general idea of what will be a good view of the Nashville skyline.
Connector Bridge
Here is a fast video showing the construction of the connector bridge between the Sheds and some other site work that has happened over the past few weeks.
Monday, April 28, 2014
Announcing First Tenant
Welcome to The Sheds, Invivolink. We are excited to have you all.
http://www.tennessean.com/story/money/real-estate/2014/04/28/invivolink-headed-sheds-charlotte/8409509/
http://www.tennessean.com/story/money/real-estate/2014/04/28/invivolink-headed-sheds-charlotte/8409509/
Wednesday, April 23, 2014
Connector Bridge
The Sheds have a connector bridge that joins the 2nd floors of the two buildings. These photos show the steel being erected for this connector.
Thursday, April 10, 2014
Concrete permieter foundations
The weather is finally cooperating enough to pour concrete. Building C perimeter is poured in preparation to start wall framing.
Site Infrastructure
We are installing all of the storm water, sewer and water infrastructure now. These are deep connections!